Allianz Field Construction Hits Halfway Mark

Allianz Field

Minnesota United FC has hit the halfway mark in the construction of Allianz Field, its new home that is set to open in 2019. 

Construction of Allianz Field is reportedly moving along, as the $200-million facility is currently expected to wrap up within budget and on time. That was reflected by a milestone achieved this week, when the facility’s construction process hit the 50% completion mark.

Plenty of work remains in the coming months, but signs of what the finished product will look like are in place. At this point, the stadium could be completed in February 2019, with Minnesota hosting its first MLS match there in April. More from the Pioneer Press:

“We’re halfway home but we have a really busy summer ahead,” project manager Greg Huber said Thursday.

The first piece of steel was raised in November after groundwork was finished.. Since then, the cement rows of the upper and lower bowls have been poured, corporate suites and club level seating is framed out, the north end beer hall is going up and the standing-only supporter’s section is coming around on the south side of the stadium.

The moonscape of the pitch is covered with limestone to accommodate the heavy cranes, earth movers and waste bins, although the intimacy of the 19,400-seat stadium is obvious. There will be little separation between fans and players.

“The aesthetic is just tremendous,” said William McGuire, Minnesota United’s primary owner. “The combination of architecture and functionality with the game-day experience is pretty overwhelming.”

Allianz Field is intended to be the anchor of a larger development plan in St. Paul’s Midway neighborhood. United FC has spent the past few years planning the soccer-specific stadium, while hosting home matches at the University of Minnesota’s TCF Bank Stadium for the 2017 and 2018 seasons–a move that gives the a home until the new facility opens.

RELATED STORIES: Garber: Allianz Field Could Host Top-Level MatchesAllianz Field Granted Noise Exemption for United FC MatchesAllianz Field Still Slated for 2019 OpeningSt. Paul Okays Infrastructure Upgrades for Allianz Field SiteMixed-Use Development Planned Outside Allianz FieldAllianz Field Votes Set for This WeekBill McGuire Buys Property at Site of Allianz Field ProjectAllianz Field Construction Moving ForwardNew for 2019: Allianz FieldTIF Money Approved for Minnesota United FC Stadium Site CleanupTIF Funds Proposed for Cleanup of Minnesota United FC Stadium SiteMinnesota United FC Stadium Groundbreaking Could Take Place This WeekMinnesota United FC Unveils Stadium Construction TimelineState Approves Tax Breaks for Minnesota United FC StadiumIrgens Could Partner on Minnesota United FC Stadium DevelopmentDon Garber: Minnesota United FC Stadium Plan Will Move ForwardPort Authority Planning Agreement Near Minnesota United FC StadiumBest of 2016, #4: Minnesota United FCMinnesota United FC Breaks Ground on New StadiumMinnesota United FC to Break Ground on New StadiumMinnesota United FC Season Ticket Sales Exceed 8,000Minnesota United FC to MLS in 2017Minnesota United unveils St. Paul MLS stadium renderings

, ,